PowNet-Thailand: Network-constrained Unit Commitment / Economic Dispatch model for the Thai power system with sample data

License

Notifications You must be signed in to change notification settings

Critical-Infrastructure-Systems-Lab/PowNet-Thailand

Repository files navigation

license MIT DOI

Note

This model is based on PowNet v1.3, which is no longer developed. If you are interested in running an instance of PowNet for the Thai power system, please check the latest release of PowNet (v2.0), which includes input data for this case study.

PowNet-Thailand: Network-constrained Unit Commitment / Economic Dispatch model for the Thai power system with sample data

PowNet-Thailand is an implementation of PowNet model on the Thai power system. The model is developed based on the load (domestic and exports) and infrastructure (power plants, substations, and high-voltage transmission lines) of the Thai power system operated in 2016, including a number of Laotian hydro and thermal power plants that supply to Thailand. The power systems’ data are mostly collected from publicly available reports, published by Electricity Generating Authority of Thailand (EGAT), Energy Policy and Planning Office (EPPO) – Thai Ministry of Energy, Electricite Du Laos (EDL), and the Department of Energy Policy and Planning (DEPP) – Laotian Ministry of Energy and Mine. The hydropower budgets are simulated with VIC-Res. Please refer to Chowdhury et al. (2021) for additional details on the power system and model setup.

For 2016, the repository contains input data, output data, and a Python script for a sample analysis. In addition, climate-dependent input data (e.g., hydropower budget) for a 30-year (1976-2005) simulation period, used in Chowdhury et al. (2021), are also provided. Outputs for any of these years can be obtained by running PowNet-Thailand through the following two steps: (1) change simulation year in ‘pownet_thai_datasetup.py’, and (2) run ‘pownet_thai_solver.py’.

The basic functionalities and input-output structure of PowNet are described in Chowdhury et al. (2020). Step-by-step instructions on how to run and customize PowNet for any power system are provided in this GitHub repository.

Citation

If you use PowNet-Thailand and/or the data for your research, please cite the following papers:

Chowdhury, A.K., Dang, T.D., Nguyen, H.T., Koh, R., and Galelli, S., (2021). The Greater Mekong's climate-water-energy nexus: how ENSO-triggered regional droughts affect power supply and CO2 emissions. Earth’s Future, 9, e2020EF001814, DOI: https://doi.org/10.1029/2020EF001814.

Chowdhury, A.K., Kern, J., Dang, T.D. and Galelli, S., (2020). PowNet: A Network-Constrained Unit Commitment/Economic Dispatch Model for Large-Scale Power Systems Analysis. Journal of Open Research Software, 8(1), p.5. DOI: http://doi.org/10.5334/jors.302.

In addition, each release of PowNet-Thailand is achieved on Zenodo with a DOI, that can be found here.

Contact

For questions and feedback related to PowNet-Thailand, please send an email to [email protected] (AFM Kamal Chowdhury) or [email protected] (Stefano Galelli).

License

PowNet-Thailand and the data are released under the MIT license.

Acknowledgment

PowNet-Thailand development is supported by Singapore's Ministry of Education (MoE) through the Tier 2 project “Linking water availability to hydropower supply – an engineering systems approach” (Award No. MOE2017-T2-1-143).