seoDescription: Do you create a Sprint Forecast? (aka The functionality that will be developed during the Sprint) - Confirming the relationship between the Product Owner and Development Team in Agile Project Management.
type: rule
title: Do you create a Sprint Forecast? (aka The functionality that will be developed during the Sprint)
title: Do you create a Sprint Forecast? (aka The functionality that will be
developed during the Sprint)
seoDescription: Do you create a Sprint Forecast? (aka The functionality that
will be developed during the Sprint) - Confirming the relationship between the
Product Owner and Development Team in Agile Project Management.
uri: sprint-forecast
authors:
- title: Adam Cogan
Expand Down Expand Up @@ -30,13 +33,13 @@ Each Sprint in a Scrum project can be considered a mini-project that has **time*

::: email-template

| | |
| -------- | --- |
| To: | {{Product Owner}} |
| Subject: | {{Client Name}}: Sprint XXX Forecast |
| | |
| -------- | -------------------------------------- |
| To: | {{ PRODUCT OWNER }} |
| Subject: | {{ CLIENT NAME }}: Sprint XXX Forecast |
::: email-content

### Hi {{Product Owner}}
### Hi {{ PRODUCT OWNER }}

Sprint Goals (in priority order):

Expand Down