help.rike.exceeded
View and manage zombies.
The Tab Graph shows all open Milestones. The vertical red line displays the current day. The bar chart of a milestone starts with the calculated beginning (due date - sum(estimated hours of all tasks)/"milestone performance") and ends with the due date. The colours show the task status (red = open, yellow = in progress, green = done).
The Tab Milestones shows all delayed milestones. The first column is the milestone id. The second column displays the name of the milestone, the work left, time left and work done in days. The third column shows the ETA (Estimated time of arrival). The value is calculated by today + sum(estimated hours of open tasks)/"milestone performance". The last column shows the delay in days.
The Tab Tasks shows all delayed tasks. You can see the task id, priority, task name, due date und delay.