Sprint 11 deliverables [9 25 to 10 7] and next sprint planning
Sumit Chachra edited this page Oct 5, 2017
·
7 revisions
High level tasks accomplished in this sprint (ending Oct. 6)
- IP Reporting Features ready for Testing. Following functionalities pending for next sprint:
- interface for reporting for joint UNICEF/Cluster indicators (see ticket for open questions)
- syncing PDs, Workspaces & Partners from PMP
- email notification to partner when a progress report is accepted/sent back
- Permission matrix, support in backend and frontend interpretation.
- Setting calculation methods for all indicators in a PD.
- Calculations for data being reported are now calculated / reflected in real-time in the frontend as the user is entering data.
- Ability to relate a location all the way up to the highest available admin level
- User sign in, profile modal, logout for all PRP users (to be used by cluster, ip, imo's, partners etc.).
- API's for all functionality PMP depends on PRP for.
- First pass of QA, bug fixes.
- UI / logic for when a progress report has been 'sent back'
- Cluster Reporting: Export for Analysis complete; initial Import Template generation complete until final import feedback is given
- Cluster Reporting: UI / frontend for managing disaggregations. Final piece of the disaggregation refactor that was done.
Timeline check
- Sep. 25: API's for PMP
- Oct. 6: PRP-IP (minus PMP integration).... functional testing
- Oct. 16: PRP<>PMP integrated.............. testing environment
- Oct. 23: Cluster PRP...................... testing environment
Sprint 12 planning
- Tasks available and ready in IP reporting in PRP milestone currently.
- Tasks available and ready in Cluster reporting in PRP milestone currently.
Open issues to discuss / agenda items
- Cluster Reporting permissions matrix needed for Sprint 12. #295
- Need Import template specifications finalized for cluster reporting: https://github.com/unicef/etools-partner-reporting-portal/issues/269
- Should we freeze any columns when generating Export for Analysis or Import Template? Those would have to be first X columns. First 4-5 rows being frozen for ease.
Goals for next sprint
- PD, Workspace, Partner Syncing from PMP
- Importing for Cluster reports (pending UNICEF final decisioning)
- Accept/Reject functionality for cluster reports
- Autocalculation of cluster activity indicators based on partner inputs
- Stretch Goal Partner Analysis section
Action points/new tickets from showcase discussions
- #155 - Gavin to share workflow.
- one set of checkboxes when reporting to both cluster and against PD.