High level tasks accomplished in this sprint (ending Oct. 20)
- Sync with PMP 75% in place.
- Dashboard refactor, bug fixes and getting it functional again.
- Prototype implementation of interface for reporting for joint UNICEF/Cluster indicators (see ticket for open questions)
- User on-boarding for both IP's, and partners/IMO's in cluster reporting along with enhanced profile modal listing relevant detail depending on whether user is partner or not.
- Started work on my planned action > activities (custom/cluster etc.). Will be finished in 2-3 days.
- Technical Making code Python 3 compatible. In PR.
- Technical API documentation in place: http://prp.tivixlabs.com/api/docs/
- Technical Getting frontend bundling to work to optimize performance on cloud environments.
- More API changes for all functionality PMP depends on PRP for.
- Second pass of QA, bug fixes.
Timeline check Change in timelines by ~10 days. Cluster PRP can still be delivered by Oct. 27, if required. PRP<>PMP integration may take development/testing effort hence being conservative.
- Oct. 27: PRP<>PMP integrated.............. testing environment
- Nov. 3: Cluster PRP...................... testing environment
Sprint 12 planning
- Tasks available and ready in IP reporting in PRP milestone currently.
- Tasks available and ready in Cluster reporting in PRP milestone currently.
Open issues to discuss / agenda items
- PMP<>PRP API dependencies: Documented here: https://github.com/unicef/etools/issues/934
- Need Import template specifications finalized for cluster reporting: https://github.com/unicef/etools-partner-reporting-portal/issues/269
Goals for next sprint
- Email notification to partners when a progress report/indicator reports is accepted/sent back and for various other things to IMO's as well. --Gavin-- summary emails are better than email for every action. unicef focal point and authorized officer in IP reporting case.
- Finish testing sync with PMP / any final changes relating to indicators/disaggs
- Importing for Cluster reports (pending UNICEF final decisioning)
- "Send back" functionality for cluster reports via IMO's
- Auto-calculation of cluster activity indicators based on partner inputs
- Cluster analysis section
- Continued QA / testing
Action points/new tickets from showcase discussions
- Dual reporting on shared indicators #155.
- Cluster analysis spec to be shared.
- Importing data in cluster on hold till MVP.
- Communicate out new dates from timeline above.